Our Latest Remediation Project

lks-16-0007

We are nearing the end of our latest Remediation and Enabling Works contract on the edge of Manchester.  Working as Principal Contractor since June 2016 we have remediated this old mill site that adjoins the River Irwell, ready for 72 new houses and two blocks of apartments.  During our 12 week programme we uncovered the relic underground structures from the old mill that was built on site and prepared the site ready for construction by our client.  We handed over a clear, secure and fully remediated site with piling mats ready for construction, which is now underway.  We look forward to seeing these award winning loft living spaces being built and breathing new life into this area of Manchester.