Japanese Knotweed – Bardsley Construction

bardsley-image

The LK Group devised a management plan which comprised a combination of treatments. Designated Area A was subject to a ‘dig and dump’ operation. A semi-permeable membrane
was installed post-excavation to protect against further growth and re-infestation. Designated Area B did not encroach on the development area, so was suitable for herbicide application.
Spraying commenced once permission was granted by the Environment Agency.